Construction of Port of Auckland’s new Bledisloe North wharf has reached a major milestone, with the first precast concrete deck panel installed as work enters its final phase.
The deck-laying programme marks the next stage of the project which will deliver Auckland’s first multi-use wharf capable of handling larger ships.
“This is a big moment for our city and a day that is worth celebrating,” Port of Auckland chief executive Roger Gray says.
“The work being done here is part of our $200 million investment to unlock economic growth through more cruise tourism and roll-on, roll-off freight capacity for greater Auckland.
“It sets us up well into the future and confirms our gateway status to the world,” he says.
The project is the first infrastructure development approved under the Government’s fast-track consenting legislation.
“Bledisloe North wharf is the first of our infrastructure projects to be approved under the fast-track legislation. From consent application to project completion will take just two years,” Gray says.
Construction is being carried out by HEB, which completed the foundation stage by installing 242 piles using more than 3,800m³ of concrete.
It involves installing 290 precast concrete panels, with about half manufactured on-site and the remainder produced off-site. Once the panels are in place, a further 2,580m³ of concrete will be poured to form the completed wharf deck.
Marine infrastructure, including fenders, bollards and wharf services, will then be installed.
Gray says the project complements the port’s new international cruise terminal, which is also progressing on schedule.
“This major infrastructure project goes hand in hand with the creation of Auckland’s newest international cruise terminal. We’re proud to share that this project is also progressing and on track for completion in early 2027.”
The Bledisloe North wharf and the new cruise terminal are both expected to open in March 2027.
Once work on Bledisloe North is complete, the port will begin extending Fergusson North under the fast-track consent granted in August 2025.