Port of Auckland has completed the first concrete deck pour for its Bledisloe North wharf as work advances on more than $200 million of infrastructure upgrades.
The first of eight planned pours covered 1255 square metres and took 13 continuous hours to complete.
The wharf project is expected to be halfway complete by Christmas and will use about 2410 cubic metres of concrete for its deck — roughly enough to fill an Olympic-sized swimming pool.
Bledisloe North is being developed as Auckland’s first large-ship, multi-use wharf, providing capacity for cruise ships and roll-on, roll-off freight vessels.
The wharf is supported by 242 piles containing more than 3800 cubic metres of concrete.
Its deck comprises 290 precast concrete panels, with about half produced on site and the remainder cast elsewhere.
Work will move to wharf services and marine infrastructure, including fenders and bollards, once the deck is finished.
Construction is also progressing on the adjoining Auckland International Cruise Terminal.
Framing, ceiling plasterboard, suspended ceilings and bulkheads have been completed, while work on heating, ventilation and air-conditioning ducting, electrical systems and data infrastructure is well advanced.

Port of Auckland chief executive Roger Gray says the projects have progressed significantly since construction began about a year ago.
“We’re getting on with our big build to grow cruise for the city and our team is making stunning progress,” Gray says.
“The wharf deck is now being poured and the terminal increasingly taking shape.”
The port has contracted Bledisloe North construction partner HEB Construction to move directly into delivering the Fergusson North extension, with preliminary work already under way.
“Together, the new wharf and terminal will give Auckland better infrastructure for larger cruise ships while also increasing the port’s capacity for roll-on, roll-off freight,” Gray says.
The wider investment programme also includes extending Fergusson North and deepening the Rangitoto shipping channel through an existing consented works package during 2027.
Gray says those projects will provide the infrastructure needed to accommodate larger container vessels.
Bledisloe North wharf and the new cruise terminal are scheduled to open officially in March 2027.